Built at a total cost of EUR 1.176 billion, the Nhon-Hanoi Railway Station project has a total length of 12.5km, comprising an 8.5km aerial track that will connect Nhon depot with Thu Le Zoo and a 4km-long underground track that will link Thu Le with the Hanoi Railway Station.

leftcenterrightdel
Secretary of the Hanoi Party Committee Hoang Trung Hai (C) at the work site. Photo: vnexpress.net

The line will start at Nhon and reach Cau Giay via Road 32 and Ho Tung Mau and Xuan Thuy streets. It will also pass through Kim Ma, Nui Truc and Quoc Tu Giam streets. The last stop will be the Hanoi Railway Station at the T-junction of Le Duan and Tran Hung Dao streets.

At a meeting with the working group as part of the inspection, Nguyen Cao Minh, head of the municipal urban rail project management board, reported that the auction of all nine bid packages of the Nhon-Hanoi Railway Station project has been completed, with eight contracts signed to date.

About 41 percent of the total construction workload was done, he said, adding that the building of the elevated track has been completed by more than 82 percent.

According to him, the project’s disbursement has amounted to over VND 7.1 trillion (EUR 260.8 million).

The first train will arrive in Hanoi in June 2020, while the construction of the underground track is expected to be finished in 2022.