The request was made during a project progress meeting on November 5.
Reporting on progress through November 2026 and outlining the next steps, Senior Colonel Nguyen Trung Kien, Deputy Director of the GDP’s Department of Logistics, said the department had taken the initiative in working with relevant agencies and units to prepare the project for investment and organize construction on various parts of the project.
    |
 |
|
Senior Lieutenant General Le Quang Minh delivers the closing remarks. |
The contractor has finished demolishing existing structures above and below ground, relocated the transformer station and built 567 meters of guide walls and 567 meters of diaphragm walls. Production pile installation began on September 13, 2026. By the time of the report, 280 of the 378 piles had been installed, accounting for 74 percent of the planned pile installations.
Four crews have been working across three shifts. Personnel, vehicles and equipment have been mobilized to keep construction on schedule and ensure quality and worker safety.
At the event, participants discussed problems that had arisen during the project, focusing on coordination among the relevant agencies, progress on completing investment documentation and procedures, and the review and approval of designs and cost estimates. They also proposed measures to resolve the problems and keep the overall project on schedule.
In his closing remarks, the GDP leader commended the Department of Logistics and the general department’s relevant agencies for taking responsibility and showing initiative in carrying out the project.
    |
 |
|
An overview of the meeting |
He said the project is a key project of great significance that had received particular attention from leaders of the Party and State, the Central Military Commission and the Ministry of National Defense. Senior Lieutenant General Le Quang Minh said the agencies and units had made considerable efforts, working carefully and systematically to resolve problems step by step and keep construction on schedule.
The GDP’s vice chairman also noted that coordination among some agencies had at times fallen short and that delays in resolving certain issues had affected the overall schedule.
He asked the GDP’s relevant agencies to take greater responsibility for leading and overseeing the work, coordinate more closely and communicate directly so they could resolve problems as they arose. Each agency and unit needs to define its responsibilities, tasks and deadlines clearly and prevent internal procedures from delaying the project.
Senior Lieutenant General Le Quang Minh requested the agencies and units to act pro-actively, flexibly and decisively while complying with the law. They should speed up construction while completing the investment documentation and procedures, and maintain construction quality as they work to meet deadlines. He also called for strict control of total investment to prevent losses and waste. He urged the agencies and units to work together and take responsibility for their shared task of building a modern cultural and arts venue with distinctive architecture that befits the military’s standing and traditions.