The nearly 519km-long line has investment capital of over 22.35 trillion VND (929 million USD), comprising four sections, including Quang Trach - Quynh Luu, Quynh Luu - Thanh Hoa, Thanh Hoa - Nam Dinh 1 thermal power plant, and Nam Dinh 1 thermal power plant - Pho Noi.

leftcenterrightdel
Prime Minister Pham Minh Chinh chairs the event.

Construction of the transmission line began in October 2023 for some sections and January 2024 for others, with a goal of completion and operation in June 2024.

Speaking at the event, PM Chinh hailed ministries and agencies, especially the Ministry of Industry and Trade, for their active role in regularly overseeing and accelerating the project.

They were asked to continue working closely together to overcome any hurdles and maintain the project's schedule.

The PM directed relevant authorities to finalize compensation policies for affected residents by April 10. He also set deadlines for substantial completion of project items by June 20 and full operation no later than June 30.