Speaking at a meeting on public investment on August 31, Ha said that public investment projects helped address issues of transport, infrastructure, environment and improve living conditions in the city.
However, slow disbursement for public investment projects reduced the efficiency of the State’s capital and land use.
Notably, only nine out of 55 key public investment projects in the city have been completed since 2016.
|
|
At the meeting (Photo: thoibaotaichinhvietnam) |
This year, the city earmarked about 28 trillion VND (1.2 billion USD) for 581 projects, Ha said, calling for drastic measures to solve problems and ensure that all funds would be disbursed by the end of the year.
Vice Chairman of the municipal People’s Committee Le Hong Son said that from 2016 to 2019, the city approved a total public investment of over 107.3 trillion VND (4.6 billion USD), of which, the city earmarked more than 79 billion VND for projects.
As much as 67.49 billion VND (2.9 billion USD), or 85.3 percent of the arranged funds, were disbursed from 2016 to the end of January 2020.
With the disbursed funding, 396 projects were completed.
In the first seven months of this year, 50 out of 155 city-level basic construction projects were completed, while another 222 projects are ongoing.
By the end of July this year, the city disbursed over 14.6 trillion VND (630.5 million USD), accounting for nearly 33 percent of planned funding, Son said.
Son said that official development assistance (ODA) projects were being implemented and disbursed slowly because from 2017, the ODA funding was allocated in line with the State’s yearly plan, not in line with the speed of projects that received the ODA.
Moreover, the ODA funding was from donors and they have to be consulted on the disbursement before selecting bidders.
Difficulties in developing relocation housing hindered land clearance activities, resulting in delayed projects.
Nguyen Cao Minh, Director of the Management Board of Urban Railway Projects, said that it put aside 5.3 trillion VND (229 million USD) for railway projects in 2019 and 2020.
Until now, just 43 percent of investment for Urban Railway Line No.3 Nhon – Hanoi Railway Station was disbursed because of COVID-19, which delayed the import of equipment from Europe.
The Line No.3 project will have 97 percent of funding disbursed by the end of this year, Minh said.
However, for the Urban Railway Line No.2 Nam Thang Long – Tran Hung Dao, its funding would not be disbursed this year because changes in the project must be submitted and approved by the National Assembly in its meeting in October 2020.
Nguyen Van Hung, Director of the city’s Investment Management Board for Water Supply, Drainage and Environment Works, said that the board was allocated 1.3 trillion VND this year but until now, just 42.3 percent of the funding was disbursed.
“Personnel capacity and investors are key factors affecting the speed of disbursement, but of 186 staff on the board, many fail to meet the job requirements,” Hung said.
For the Yen Xa waste water treatment project, just 40 percent of total investment was disbursed because it had to open bidding twice with the first bidding results removed and the second bidding results helping save over 900 billion VND.
Chairwoman of the Hanoi People’s Council Nguyen Thi Bich Ngoc said that the city’s public investment during 2016-2020 was very important to the development of the city and the country as well, because funding for the city’s public investment accounted for ten percent of the country’s public investment fund.
At this time, public investment would help boost economic growth, support enterprises and create more jobs.
Source: VNA