May 10, 2008 | 21:58 (GMT+7)
Border patrol route constructed
PANO – The management board of the Border Patrol Project 47 of the General Staff has met to work out plans for implementing projects in 2008.
PANO – The management board of the Border Patrol Project 47 of the General Staff has met to work out plans for implementing projects in 2008.
A patrol route of 14,254km long, running through 25 provinces from Quang Ninh to Kien Giang province will be built.
Head of the project management board, Major General Hoang Kien, said in his report that 10 projects to construct the patrol routes had been given to 42 companies including 14 engineers corps and 28 military construction companies since Nov 2007.
In 2008, 13 projects were given to 63 construction units.
Translated by Hoang Anh