leftcenterrightdel
The Cat Hiep solar power plant

The 49.5 MWp plant, spanning 60.1 ha in Cat Hiep commune, Phu Cat district, is connected to the grid at the 110 kV Phu Cat power station via a 5.5 km wire system.

The entire project was built at a cost of 1.1 trillion VND (47.3 million USD), invested mainly by France-based Quadran International and Vietnam’s Truong Thanh Group.

The plant is scheduled to begin its commercial operation on June 6, producing between 78,000 and 80,000 MWh of electricity for the grid on an annual basis.

Source: VNA