Ministry to open bids on five PPP projects for North-South Expressway in October
The Ministry of Transport is scheduled to open bids on five public-private partnership (PPP) component projects of the North-South Expressway from October 2-5.
|
|
The Ministry of Transport is scheduled to open bids on five PPP component projects of the North-South Expressway from October 2-5. (Photo for illustration) |
Adjustments to bidding documents for the projects are expected to be ratified on September 18-20.
Project management boards informed the short-listed investors on July 20-21, who have 60 days to prepare.
The ministry will negotiate and sign contracts with investors in December, with construction to begin in early 2021 and complete in 2023, as set by the National Assembly and the Government.
The five component projects cover five sections along the North-South Expressway: National Highway No.45 - Nghi Son (Thanh Hoa), Nghi Son - Dien Chau (Nghe An), Dien Chau - Bai Vot (Ha Tinh), Nha Trang - Cam Lam (Khanh Hoa), and Cam Lam - Vinh Hao (Binh Thuan).
The North-South Expressway project has a total length of 654km and is divided into 11 sub-projects, including six under public investment and five under PPP. Investment for the sub-projects totals 100.8 trillion VND (4.3 billion USD), of which 78.4 trillion VND is from the State budget.