Dung said the work must be carried out under the province’s authority, and in accordance with the existing laws.

leftcenterrightdel
Loc An - Binh Son resettlement area is under construction.

Dong Nai should join hands with the Ministry of Transport, the Airports Corporation of Vietnam and competent agencies to implement component projects to ensure efficiency and progress of Long Thanh Airport construction.

Construction of the first detail of Long Thanh International Airport starts on January 5.

The airport will be built in three phases over three decades, and is expected to become the country’s largest airport.

In the first phase, one runway with a length of 4,000m, taxiways, an apron, and a passenger terminal with other auxiliary works sprawling 373,000 sq.m will be built to serve 25 million passengers and 1.2 million tonnes of cargo each year.

The airport is designed to have four runways, four passenger terminals, and other auxiliary facilities to ensure a capacity of 100 million passengers and 5 million tons of cargo a year by 2040.

Covering a total area of more than 5,580ha, the airport will straddle six communes in Long Thanh district. It is expected to cost 336.63 trillion VND (14.5 billion USD), with the first phase needing over 109 trillion VND.

Around 4,800 households and 26 organizations are expected to be relocated to make way for it.

Located 40km to the east of Ho Chi Minh City, Long Thanh airport is expected to relieve overloading at Tan Son Nhat International Airport in the southern metropolis, now the country’s largest airport.

Source: VNA