Vietnam’s Engineering Company Rotation 1 installs security fencing in Abu Qussa
PANO - After 14 working days with sense of urgency, Vietnam’s Engineering Company Rotation 1 at the United Nations Interim Security Force for Abyei (UNISFA) has completed installing a 380m-long metal security fencing around a UNISFA military observation station in Abu Qussa.
The fencing is made from 127 Y-shaped, 126 I-shaped columns and one 5-meter wide gate. It lies about 500km away from the unit’s position on the border between South Sudan and Sudan. The observation station is located here to monitor how concerned parties observe peace agreements along the border.
Thanks to the highest responsibility and smoothly collaboration between the Vietnamese engineering unit and relevant agencies of UNISFA, the work was completed six days ahead of the initial plan with absolute safety for people and vehicles.
According to Senior Colonel Mac Duc Trong, Commanding Officer of Vietnam’s Engineering Company Rotation 1, the task force this time consisted of 17 officers, commanded by Captain Nguyen Van Khai, Leader of the Construction Engineering Detachment No.1. The unit has made good preparations in logistics and technical affairs, ensuring sufficient provision of tools and equipment, he added.
An observation station of UNISFA is placed here to monitor how concerned parties observe peace agreements along the border.
According to Senior Colonel Trong, the whole unit has promoted solidarity, unity, responsibility, independence, and creativeness to fulfill its assigned mission.
The People’s Army Newspaper would like to introduce some images of Vietnam’s Engineering Company Rotation 1 conducting their task.
|
|
Senior Colonel Mac Duc Trong, Commanding Officer of Vietnam’s Engineering Company Rotation 1, assigns missions to the unit’s forces. |
|
|
The company’s personnel implements missions in Abu Qussa. |
|
|
Leader of the Construction Engineering Detachment No.1 assigns tasks to his personnel. |
|
|
Technical materials and equipment of the company are transported to the area by helicopter. |
|
|
Technical materials and equipment are gathered at the right place. |
|
|
Members of Engineering Company Rotation 1 build the fencing under hot weather. |
|
|
The fencing is built with technical standards. |
|
|
The fencing building is finished. |
Translated by Trung Thanh